Signs of progress on St. Charles Avenue

From the Times-Picayune:

"The first step in the long road to restoration for the St. Charles Avenue streetcar line is set to take place today, as transit officials bring back daily service between Canal Street and Lee Circle for the first time since Hurricane Katrina.

Scheduled for 10:30 a.m., the ceremonial trip around Robert E. Lee's statue marks the completion of the initial phase of a three-part reformation project expected to last at least another 15 months.

Under plans still being developed, the Regional Transit Authority hopes to reopen a second leg of the historic St. Charles line, between Lee Circle and Napoleon Avenue, by next summer. The final segment, which will restore service from Napoleon to the terminus on Carrollton Avenue, likely won't be finished until spring or early summer of 2008, officials said."